High Potential Stress Test Procedure (HI-POT)

        TABLE OF CONTENTS 
        PARA.  TITLE
         1.0   PURPOSE
         2.0   SCOPE 
         3.0   REFERENCE DOCUMENTS
         4.0   PRECAUTIONARY INSTRUCTIONS
         5.0   EQUIPMENT REQUIRED 
         6.0   TEST REQUIREMENTS
         7.0   GROUND CONTINUITY
         8.0   HIGH POTENTIAL STRESS
         9.0   RECORD KEEPING REQUIREMENTS
        10.0   UNIT IDENTIFICATION
1.0 PURPOSE
    THE PURPOSE OF THIS PROCEDURE IS TO PROVIDE THE INSTRUCTIONS NEEDED TO
    PERFORM A COMPLETE AND THOROUGH HIGH POTENTIAL STRESS TEST AND A GROUND
    CONTINUITY VERIFICATION IN ORDER TO INSURE COMPLIANCE WITH THE SYSTEM
    REQUIREMENTS.  
2.0 SCOPE  
    THIS PROCEDURE DEFINES THE METHOD FOR CHECKING THE GROUND CONTINUITY, THE
    HIGH POTENTIAL STRESS CAPABILITY AND THE ASSOCIATED RECORD KEEPING THAT IS
    REQUIRED TO BE PERFORMED ON THE EAGLE POWER SUPPLY SUB-ASSEMBLY. 
3.0 REFERENCE DOCUMENTS 
    500713 PRODUCT SPEC BASE UNIT P/S                                    
    502046 SYSTEM SPEC DESK TOP COMPUTER                                 
    502077 DESIGN SPEC BASE P/S                                          
    503132 TEST SPEC BASE P/S                                            
    907472 POWER SUPPLY ASSY DTC                                         
    903394 PCBA P/S CONTROL MODULE                                       
    903404 LD P/S CONTROL MODULE                                         
    903443 PCBA P/S INPUT MODULE                                         
    903444 LD P/S INPUT MODULE                                           
    903445 PCBA P/S OUTPUT MODULE                                        
    903446 LD P/S OUTPUT MODULE                                          
    QA00-50002 UL/CSA COMPLIANCE
4.0 PRECAUTIONARY INSTRUCTIONS
    4.1   DANGEROUS VOLTAGES WILL BE PRESENT DURING THESE TESTS! IT IS
          IMPERATIVE THAT THE TEST OPERATOR BE ALERT, PAY CLOSE ATTENTION AND 
          REMAIN FREE FROM ANY DISTRACTION DURING THE PERFORMANCE OF THESE
          TESTS.                         
    4.2   UNAUTHORIZED PERSONNEL SHOULD BE RESTRICTED FROM THE  AREA WHEN
          THESE TESTS ARE IN PROCESS.                          
    4.3   EQUIPMENT, CABLES AND ACCESSORIES SHOULD BE CHECKED AT FREQUENT
          INTERVALS FOR WEAR, DAMAGED INSULATION OR ANY CONDITION THAT COULD 
          BE CONSIDERED UNSAFE.           
    4.4   THE TEST AREA SHOULD BE KEPT CLEAR AND UNCLUTTERED. ALL UNNESSARY
          EQUIPMENT AND TOOLS SHOULD BE REMOVED FROM THE TEST AREA.  
    4.5   IT IS IMPORTANT THAT ALL CABLES AND CONNECTORS ARE PROPERLY
          IDENTIFIED AND CONNECTED CORRECTLY PRIOR TO THE APPLICATION OF
          POWER, OTHERWISE DAMAGE, ERRONEOUS INDICATIONS OR EVEN INJURY COULD
          RESULT.
5.0 EQUIPMENT REQUIRED
    5.1   A HIGH POTENTIAL STRESS TESTER WITH THE CAPABILITY OF:      
             A) DELIVERING AND SUSTAINING THE SPECIFIED VOLTAGE FOR THE
                REQUIRED LENGTH OF TIME.                      
             B) A METER THAT INDICATES THE VOLTAGE AT THE OUTPUT CONNECTIONS. 
             C) AN INDICATOR, EITHER VISUAL OR AUDIBLE, TO INDICATE A
                BREAKDOWN.                                 
             D) ABLE TO BE CALIBRATED.                                
    5.2   AN ADAPTER CABLE TO CONNECT THE HI-POT TESTER TO THE DEVICES UNDER
          TEST, WITH THE FOLLOWING:                     
              A) AN OUTPUT CONNECTOR THAT WILL MATE DIRECTLY WITH THE AC INPUT
                 RECEPTACLE OF THE UNITS UNDER TEST.      
              B) A HIGH VOLTAGE INSULATED WIRE CONNECTING THE GROUND SIDE OF 
                 THE TESTER TO THE GROUND PIN OF THE OUTPUT CONNECTOR.   
              C) A HIGH VOLTAGE INSULATED WIRE CONNECTING THE OUTPUT SIDE OF
                 THE TESTER TO BOTH THE AC LINE AND AC NEUTRAL PINS OF THE
                 OUTPUT CONNECTOR.                         
    5.3   A GROUNDING CONNECTOR THAT WILL BE CAPABLE OF CONNECTING SIGNAL
          GROUND TO CHASSIS GROUND.                            
    5.4   A CLOCK OR WATCH CAPABLE OF DISPLAYING SECONDS.             
    5.5   AN OHMMETER CAPABLE OF MEASURING AS LOW AS 0.1 OHMS.
6.0 TEST REQUIREMENTS 
    6.1   ALL EAGLE POWER SUPPLIES MUST BE TESTED AND PASS THE GROUND 
          CONTINUITY AND HIGH POTENTIAL STRESS (HI-POT) TESTS BEFORE BEING
          INSTALLED IN A SYSTEM, SENT TO STOCK OR SHIPPED AS A SPARE UNIT.
    6.2   ANY UNIT THAT FAILS EITHER THE GROUND CONTINUITY TEST OR THE HIGH
          POTENTIAL STRESS TEST MUST HAVE ALL DEFECTS IDENTFIED AND REPAIRED.
          AFTER REPAIR, THE UNIT MUST BE RETESTED AND PASS BOTH TESTS.   
    6.3   ANY POWER SUPPLY ASSEMBLY THAT HAS HAD UPDATING, REPAIR,
          MODIFICATION OR CHANGES OF ANY KIND TO THE INTERNAL COMPONENTS, 
          SHALL REQUIRE RETESTING FOR BOTH GROUND CONTINUITY AND HI-POT. 
7.0 GROUND CONTINUITY
    7.1   VERIFY THAT THE UNIT UNDER TEST IS CLEAR OF ANY EQUIPMENT, CABLES OR
          OTHER MATERIALS ON THE TEST STATION AND THAT THERE ARE NO ELECTRICAL
          CONNECTIONS TO THE UNIT.                                    
    7.2   USING A METER CAPABLE OF MEASURING OHMS AS LOW AS 0.1 OHMS, SET THE 
          METER TO THE OHMS FUNCTION AND TO THE LOWEST SCALE AVAILABLE. 
    7.3   CONNECT THE COMMON PROBE OF THE METER SECURELY TO ANY CONVENIENT
          POINT ON THE SHEET METAL CHASSIS OF THE UNIT UNDER TEST.  
    7.4   CONNECT THE OTHER PROBE OF THE OHMMETER TO THE GROUND PIN OF THE AC
          POWER INPUT CONNECTOR.                 
    7.5   TO PASS, THE RESISTANCE MEASURED BETWEEN THE GROUND PIN OF THE POWER
          INPUT CONNECTOR AND THE METAL CHASSIS MUST BE 0.2 OHMS OR LESS. 
    7.6   IF THE UNIT UNDER TEST FAILS THE GROUND CONTINUITY TEST, DO NOT RUN 
          THE HI-POT TEST.
8.0 HIGH POTENTIAL STRESS (HI-POT TEST)
    8.1   VERIFY THAT THE UNIT UNDER TEST IS CLEAR OF ANY EQUIPMENT, CABLES OR
          OTHER MATERIALS ON THE TEST STATION AND THAT THERE ARE NO ELECTRICAL
          CONNECTIONS TO THE UNIT.                                    
    8.2   TURN ON THE HI-POT TESTER.                                  
    8.3   SET THE OUTPUT VOLTAGE OF THE HI-POT TESTER TO 1450 VOLTS DC.  
    8.4   TURN OFF THE HI-POT TESTER.                                 
    8.5   PLACE THE POWER SWITCH OF THE UNIT UNDER TEST TO THE ON POSITION. 
    8.6   CONNECT THE HI-POT TESTER ADAPTER CABLE TO THE AC INPUT RECEPTACLE
          OF THE UNIT UNDER TEST.                 
    8.7   CONNECT THE GROUNDING CONNECTOR TO P1 OF THE POWER SUPPLY UNDER
          TEST. THEN, FIRMLY CONNECT THE ALLIGATOR CLIP OF THE GROUNDING 
          CONNECTOR TO ANY CONVENIENT POINT ON THE METAL CHASSIS OF THE UNIT
          UNDER TEST, THAT WILL PROVIDE A SOLID GROUND CONNECTION.          
    8.8   TURN ON THE HI-POT TESTER AND ALLOW TO RUN FOR 60 SECONDS.  
    8.9   AFTER THE 60 SECONDS, TURN OFF THE HI-POT TESTER.           
    8.10  DISCONNECT THE UNIT UNDER TEST FROM THE TESTER.             
    8.11  DISCONNECT THE GROUNDING CONNECTOR FROM THE UNIT UNDER TEST. 
    8.12  TO PASS, THE UNIT UNDER TEST MUST BE EXPOSED TO A MININUM STRESS OF
          1414 VDC FOR 60 SECONDS WITHOUT ANY INDICATION OF BREAKDOWN.
9.0 RECORD KEEPING REQUIREMENTS 
    A LOG MUST BE KEPT ON ALL EAGLE POWER SUPPLY UNITS TESTED FOR GROUND
    CONTINUITY AND HIGH POTENTIAL STRESS. THIS LOG MUST BE CONTAIN THE
    FOLLOWING INFORMATION:    
    9.1   THE COMPLETE SERIAL NUMBER OF THE UNIT TESTED WHICH INCLUDES THE
          FACTORY ORDER AND SERIAL NUMBER.               
    9.2   GROUND CONTINUITY PASS OR FAIL CHECK-OFF.                   
    9.3   HIGH POTENTIAL STRESS PASS OR FAIL CHECK-OFF.               
    9.4   THE DATE THE TEST WAS PERFORMED.                            
    9.5   THE NAME OR IDENTIFYING STAMP OF THE TECHNICIAN THAT PERFORMED THE 
          TEST. 
          A SAMPLE OF A RECOMENDED LOG SHEET IS SHOWN BELOW
   __________________________________________________________________________
  |                                                                          |
  |     SERIES 2000 POWER SUPPLY HI-POT & GROUND CONTINUITY LOG SHEET        |
  |                                                                          |
  |                                                                          |
  |   UNIT      |GND CONT | HI-POT  |  PARTS   |RETEST |   DATE   |   TEST   |
  |  SERIAL #   | (check) | (check) | REPLACED |  OK   |  PASSED  | OPERATOR |
  | (COMPLETE)  |PASS|FAIL|PASS|FAIL|          |(check)|          |          |
  |==========================================================================|
  |             |    |    |    |    |          |       |          |          |
  |--------------------------------------------------------------------------|
  |             |    |    |    |    |          |       |          |          |
  |--------------------------------------------------------------------------|
  |             |    |    |    |    |          |       |          |          |
  |--------------------------------------------------------------------------|
  |             |    |    |    |    |          |       |          |          |
  |--------------------------------------------------------------------------|
10.0 UNIT IDENTIFICATION                                              
                                                                              
    10.1  ALL POWER SUPPLY ASSEMBLIES THAT HAVE PASSED THE GROUND CONTINUITY
          AND HI-POT TESTS SHALL BE MARKED SO THAT THEY CAN BE READILY
          IDENTIFIED.                     
    10.2  THE MARKING MAY BE IN THE FORM OF AN ADHESIVE LABEL WITH PRINTING,
          SUCH AS "HIPOT OK".                          
    10.3  THE LABELS SHALL BE PLACED ON THE SHEET METAL SURFACE OF THE REAR
          PANEL OF THE POWER SUPPLY WITHIN AN AREA THAT WILL NOT BE COVERED
          BY THE SYSTEM'S REAR COVER.